Day 12: Drainage going in


Went past the block this morning and saw a truck parked out front with a whole bunch of plumbing materials unloaded onto the nature strip.

We stopped the car and saw there were a couple of guys busily laying the underground storm water & sewer piping.

Continue reading “Day 12: Drainage going in”


Site Start Dates

We received our site start dates from Carlisle today!

Temp Fence and Banner 4th March
Site Cut and Toilet 7th March
Set out and Bin 9th March
Electrical Connection 11th March
Drains 17th March
Slab Start 21st March
Slab Pour 23rd March