30-Mar-15 Initial deposit
09-May-15 Colour Browse Appointment
15-Jul-15 Colour Selection Appointment
18-Aug-15 Initial Tender Appointment
15-Sep-15 Second Tender Appointment
06-Oct-15 Initial Contract Meeting
26-Oct-15 Electrical Service Abolished
27-Oct-15 Contract signing
02-Nov-15 Gas Service Abolished
30-Nov-15 Demolition Commences with Asbestos Removal
16-Dec-15 Demolition Complete
7-Mar-16 Official Construction Start
26-Mar-16 Base Stage Complete
4-Apr-16 Frame Start
Advertisements